- Launched
- Jun 20183 yrs 6 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 5 yrs 3 mths
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 2
- 3 BHK
- 11
- Total units
- 14
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 97% | – | |
| 100% | 100% | 97% | – | |
| 100% | 100% | 97% | 1 |
"–" means MahaRERA shows no figure for that update.
About this project
Dharam Castle by Bhurji Developers LLP is a 14-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in June 2018 with possession due in March 2027. The concrete structure (RCC) is complete.
Read full summary
Dharam Castle is a BMC-sanctioned project by Bhurji Developers LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51900016656. It was launched in June 2018. It has 14 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 5 years 3 months from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.