Dharam Castle, Grant Road

Ready to move

by Bhurji Developers LLP · Grant Road, Mumbai 400007 · Map

Launched
Jun 20183 yrs 6 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 5 yrs 3 mths
Concrete structure
100%Ready to move
Booked
–
Buildings
10.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
2
3 BHK
11
Total units
14
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services97%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 97%Dec 2025: Final finishes 97%Jul 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 100%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%97%–
100%100%97%–
100%100%97%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dharam Castle by Bhurji Developers LLP is a 14-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in June 2018 with possession due in March 2027. The concrete structure (RCC) is complete.

Read full summary

Dharam Castle is a BMC-sanctioned project by Bhurji Developers LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51900016656. It was launched in June 2018. It has 14 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 5 years 3 months from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.