Shankheshwar Heights, Sion
by Siddheshwar Construction Co · Sion, Mumbai 400022 · Map
- Launched
- Oct 20187 yrs 8 mths originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- 87 of 13067%
- Buildings
- 40.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 99
- 3 BHK
- 21
- Other units
- 10
- Total units
- 130
- Buildings
- 4
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 68% | 87 | |
| 100% | 84% | 66% | 87 | |
| 100% | 85% | 19% | – | |
| 100% | 85% | 19% | 193 |
"–" means MahaRERA shows no figure for that update.
About this project
Shankheshwar Heights by Siddheshwar Construction Co is a 130-unit SRA-sanctioned project in Sion, Mumbai 400022, launched in October 2018 with possession due in June 2027. 87 units booked out of total 130 units. The concrete structure (RCC) is complete.
Read full summary
Shankheshwar Heights is an SRA-sanctioned project by Siddheshwar Construction Co in Sion, Mumbai 400022, registered with MahaRERA as P51900018161. It was launched in October 2018. It has 130 units in 4 buildings: 120 homes (2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, extended by 1 year from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 68% complete.
87 units booked out of total 130 units (67%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 84% to 100%.