Naman Xana, Worli

Ready to move

by Shree Naman Residency Pvt Ltd · Worli, Mumbai 400018 · Map

Launched
Dec 20188 yrs 8 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
100%Ready to move
Booked
–
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

5+ BHK
17
Total units
17
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 43%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 5%Dec 2025: Final finishes 20%Jul 2026: Final finishes 30%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%80%30%–
100%80%20%–
100%43%5%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Naman Xana by Shree Naman Residency Pvt Ltd is a 17-unit BMC-sanctioned project in Worli, Mumbai 400018, launched in December 2018 with possession due in August 2027. The concrete structure (RCC) is complete.

Read full summary

Naman Xana is a BMC-sanctioned project by Shree Naman Residency Pvt Ltd in Worli, Mumbai 400018, registered with MahaRERA as P51900018769. It was launched in December 2018. It has 17 units in 1 building, with 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 80% to 100%.