- Launched
- Mar 20194 yrs 11 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 2 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 10 of 1856% · 20 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 18 units
Rehab20 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 RK
- 8
- 1 BHK
- 10
- 2 BHK
- 12
- 3 BHK
- 8
- Total units
- 38
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 18
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 10 | |
| 100% | 100% | 90% | 1 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
Som Niwas by Naman Developers is a 38-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in March 2019 with possession due in April 2027. 10 units booked out of 18 units for sale. The concrete structure (RCC) is complete.
Read full summary
Som Niwas is a BMC-sanctioned project by Naman Developers in Dadar East, Mumbai 400014, registered with MahaRERA as P51900019850. It was launched in March 2019. It has 38 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 18 are for sale and 20 are rehab units for existing members.
Its registered possession date is April 2027, extended by 3 years 2 months from the original February 2024. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
10 units booked out of 18 units for sale (56%). Since the July 2026 update, 9 more units have been booked and the possession date has moved from December 2024 to April 2027.