Ananta Heights, Kalbadevi
by Jdj-Vishal · Kalbadevi, Mumbai 400002 · Map
- Launched
- Mar 20194 yrs originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 3 yrs 9 mths
- Concrete structure
- 89%Mid-construction
- Booked (free sale)
- 24 of 4159% · 63 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 41 units
Rehab63 units for existing members
Total 104 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 77
- 2 BHK
- 22
- Other units
- 5
- Total units
- 104
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 41
- Rehab units
- 63
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 10% | 24 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 12 |
"–" means MahaRERA shows no figure for that update.
About this project
Ananta Heights by Jdj-Vishal is a 104-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in March 2019 with possession due in December 2026. 24 units booked out of 41 units for sale. The concrete structure (RCC) is 89% complete.
Read full summary
Ananta Heights is a BMC-sanctioned project by Jdj-Vishal in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900019919. It was launched in March 2019. It has 104 units in 1 building: 99 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 104 units, 41 are for sale and 63 are rehab units for existing members.
Its registered possession date is December 2026, extended by 3 years 9 months from the original March 2023. Construction: excavation complete, structure (RCC) 89% complete, final finishes 10% complete.
24 units booked out of 41 units for sale (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 89% and the possession date has moved from June 2026 to December 2026.