Sanghvi Parsssva Excellensea, Girgaon
by Sanghvi Parsssva Enterprise LLP · Girgaon, Mumbai 400004 · Map
- Launched
- Apr 20194 yrs 8 mths originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 3 yrs 7 mths
- Concrete structure
- 70%Mid-construction
- Booked
- 8 of 1650%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 1
- 3 BHK
- 10
- Other units
- 4
- Total units
- 16
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 39% | 8 | |
| 100% | 70% | 39% | 8 | |
| 100% | 65% | 15% | – | |
| 100% | 13% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Sanghvi Parsssva Excellensea by Sanghvi Parsssva Enterprise LLP is a 16-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in April 2019 with possession due in July 2027. 8 units booked out of total 16 units. The concrete structure (RCC) is 70% complete.
Read full summary
Sanghvi Parsssva Excellensea is a BMC-sanctioned project by Sanghvi Parsssva Enterprise LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900020397. It was launched in April 2019. It has 16 units in 1 building: 12 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2027, extended by 3 years 7 months from the original December 2023. Construction: excavation complete, structure (RCC) 70% complete, final finishes 39% complete.
8 units booked out of total 16 units (50%).