Sanghvi Parsssva Excellensea, Girgaon

by Sanghvi Parsssva Enterprise LLP · Girgaon, Mumbai 400004 · Map

Launched
Apr 20194 yrs 8 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 3 yrs 7 mths
Concrete structure
70%Mid-construction
Booked
8 of 1650%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
1
3 BHK
10
Other units
4
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services39%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 13%Dec 2025: Concrete structure (RCC) 65%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 15%Jul 2026: Final finishes 39%Oct 2026: Final finishes 39%Excavation 100%Concrete structure (RCC) 70%Final finishes 39%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%39%8
100%70%39%8
100%65%15%–
100%13%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sanghvi Parsssva Excellensea by Sanghvi Parsssva Enterprise LLP is a 16-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in April 2019 with possession due in July 2027. 8 units booked out of total 16 units. The concrete structure (RCC) is 70% complete.

Read full summary

Sanghvi Parsssva Excellensea is a BMC-sanctioned project by Sanghvi Parsssva Enterprise LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900020397. It was launched in April 2019. It has 16 units in 1 building: 12 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 3 years 7 months from the original December 2023. Construction: excavation complete, structure (RCC) 70% complete, final finishes 39% complete.

8 units booked out of total 16 units (50%).