Siddha Sky, Wadala East
by Sejal Shakti Realtors LLP · Wadala East, Mumbai 400037 · Map
- Launched
- May 2019First of 5 phases
- Possession (MahaRERA)
- Jun 2026 – Dec 2030Extended in 3 of 5 phases
- Concrete structure
- 65%Weighted across 5 phases
- Booked
- 1,160 of 1,72467% · 1,059 in Jul 2026
- Buildings
- 55.8 acres
- MahaRERA complaints
- 35Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 464
- 2 BHK
- 862
- 3 BHK
- 359
- 4 BHK
- 5
- Other units
- 34
- Total units
- 1,724
- Buildings
- 5
- Land
- 5.8 acres
- Phases
- 5
- MahaRERA complaints
- 35
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Siddha Sky Phase 1 Ready to move Lapsed | P51900021027 | 357 | 100% | 89% | |
| Siddha Sky Phase 2 Nearing possession | P51900021040 | 369 | 100% | 89% | |
| Siddha Sky Phase 3 Nearing possession | P51900021044 | 328 | 100% | 85% | |
| Siddha Sky Phase 4 Early stage | P51900021031 | 360 | 0% | 16% | |
| Siddha Sky Phase V Mid-construction | P51900055793 | 276 | 18% | 54% |
Show updates by phase
Siddha Sky Phase 1 (P51900021027)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 318 | |
| 100% | 100% | 97% | 318 | |
| 100% | 100% | 10% | 318 | |
| 100% | 100% | 0% | 309 |
"–" means MahaRERA shows no figure for that update.
Siddha Sky Phase 2 (P51900021040)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 35% | 330 | |
| 100% | 100% | 25% | 330 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 305 |
"–" means MahaRERA shows no figure for that update.
Siddha Sky Phase 3 (P51900021044)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 303 | |
| 100% | 90% | 0% | 277 | |
| 100% | 90% | 0% | – | |
| 100% | 80% | 0% | 246 |
"–" means MahaRERA shows no figure for that update.
Siddha Sky Phase 4 (P51900021031)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 45% | 0% | 0% | 60 | |
| 40% | 0% | 0% | 40 | |
| 0% | 0% | 0% | 37 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Siddha Sky Phase V (P51900055793)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 149 | |
| 0% | 0% | 0% | 94 | |
| 0% | 0% | 0% | 60 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Siddha Sky by Sejal Shakti Realtors LLP is a 1,724-unit SRA-sanctioned project in Wadala East, Mumbai 400037, registered with MahaRERA in 5 phases, with possession dates from June 2026 to December 2030. 1,160 units booked out of total 1,724 units. The concrete structure (RCC) is 65% complete.
Read full summary
Siddha Sky is an SRA-sanctioned project by Sejal Shakti Realtors LLP in Wadala East, Mumbai 400037, registered with MahaRERA as 5 phases (P51900021027, P51900021031, P51900021040, P51900021044, P51900055793). The first phase was launched in May 2019. Together the phases have 1,724 units in 5 buildings: 1,690 homes (1, 2, 3 and 4 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 4 are active and 1 is lapsed.
The phases' registered possession dates run from June 2026 to December 2030; 3 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 65% complete and final finishes 29% complete. 3 of the 5 phases have their structure complete.
1,160 units booked out of total 1,724 units (67%). Since the July 2026 update, 101 more units have been booked.