Siddha Sky, Wadala East

by Sejal Shakti Realtors LLP · Wadala East, Mumbai 400037 · Map

Launched
May 2019First of 5 phases
Possession (MahaRERA)
Jun 2026 – Dec 2030Extended in 3 of 5 phases
Concrete structure
65%Weighted across 5 phases
Booked
1,160 of 1,72467% · 1,059 in Jul 2026
Buildings
55.8 acres
MahaRERA complaints
35Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
464
2 BHK
862
3 BHK
359
4 BHK
5
Other units
34
Total units
1,724
Buildings
5
Land
5.8 acres
Phases
5
MahaRERA complaints
35

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Siddha Sky Phase 1
Ready to move Lapsed
P51900021027357100%89%
Siddha Sky Phase 2
Nearing possession
P51900021040369100%89%
Siddha Sky Phase 3
Nearing possession
P51900021044328100%85%
Siddha Sky Phase 4
Early stage
P519000210313600%16%
Siddha Sky Phase V
Mid-construction
P5190005579327618%54%
Show updates by phase

Siddha Sky Phase 1 (P51900021027)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%318
100%100%97%318
100%100%10%318
100%100%0%309

"–" means MahaRERA shows no figure for that update.

Siddha Sky Phase 2 (P51900021040)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%330
100%100%25%330
100%100%0%–
100%100%0%305

"–" means MahaRERA shows no figure for that update.

Siddha Sky Phase 3 (P51900021044)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%303
100%90%0%277
100%90%0%–
100%80%0%246

"–" means MahaRERA shows no figure for that update.

Siddha Sky Phase 4 (P51900021031)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
45%0%0%60
40%0%0%40
0%0%0%37
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Siddha Sky Phase V (P51900055793)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%0%149
0%0%0%94
0%0%0%60
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation88%
Concrete structure (slabs)65%
Finishes, lifts and services29%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 62%Dec 2025: Excavation 62%Jul 2026: Excavation 71%Oct 2026: Excavation 88%Dec 2024: Concrete structure (RCC) 58%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 65%Dec 2024: Final finishes 0%Dec 2025: Final finishes 2%Jul 2026: Final finishes 26%Oct 2026: Final finishes 29%Excavation 88%Concrete structure (RCC) 65%Final finishes 29%

How to read construction stages

About this project

Siddha Sky by Sejal Shakti Realtors LLP is a 1,724-unit SRA-sanctioned project in Wadala East, Mumbai 400037, registered with MahaRERA in 5 phases, with possession dates from June 2026 to December 2030. 1,160 units booked out of total 1,724 units. The concrete structure (RCC) is 65% complete.

Read full summary

Siddha Sky is an SRA-sanctioned project by Sejal Shakti Realtors LLP in Wadala East, Mumbai 400037, registered with MahaRERA as 5 phases (P51900021027, P51900021031, P51900021040, P51900021044, P51900055793). The first phase was launched in May 2019. Together the phases have 1,724 units in 5 buildings: 1,690 homes (1, 2, 3 and 4 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 4 are active and 1 is lapsed.

The phases' registered possession dates run from June 2026 to December 2030; 3 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 65% complete and final finishes 29% complete. 3 of the 5 phases have their structure complete.

1,160 units booked out of total 1,724 units (67%). Since the July 2026 update, 101 more units have been booked.