Krishvi Escape, Kalbadevi
by Shagun Realty · Kalbadevi, Mumbai 400002 · Map
- Launched
- Dec 20197 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 92 of 13668% · 385 rehab units
- Buildings
- 11.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale92 booked out of 136 units
Rehab385 units for existing members
Total 521 units. Rehab units are not for sale.
Project facts
- 1 RK
- 19
- 1 BHK
- 289
- 2 BHK
- 47
- 3 BHK
- 80
- 4 BHK
- 6
- Other units
- 80
- Total units
- 521
- Buildings
- 1
- Land
- 1.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 136
- Rehab units
- 385
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 92 | |
| 50% | 50% | 5% | 89 | |
| 50% | 33% | 0% | 82 | |
| 100% | 20% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Krishvi Escape by Shagun Realty is a 521-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in December 2019 with possession due in December 2026. 92 units booked out of 136 units for sale. The concrete structure (RCC) is complete.
Read full summary
Krishvi Escape is a BMC-sanctioned project by Shagun Realty in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900023229. It was launched in December 2019. It has 521 units in 1 building: 441 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 80 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 521 units, 136 are for sale and 385 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.
92 units booked out of 136 units for sale (68%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 100%.