Skip to main content

Sigma Garnet, Dadar West

by Colo Color Private Limited · Dadar West, Mumbai 400028 · Map

Launched
Dec 20197 yrs originally promised
Possession (MahaRERA)
Apr 2030Extended by 3 yrs 4 mths
Concrete structure
100%Nearing possession
Booked (free sale)
64 of 10660% · 76 rehab units
Buildings
20.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale64 booked out of 106 units

Rehab76 units for existing members

Total 182 units. Rehab units are not for sale.

Project facts

1 BHK
44
2 BHK
108
Other units
30
Total units
182
Buildings
2
Land
0.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
106
Rehab units
76

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%64
100%85%50%37
100%100%50%37
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sigma Garnet by Colo Color Private Limited is a 182-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in December 2019 with possession due in April 2030. 64 units booked out of 106 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sigma Garnet is a BMC-sanctioned project by Colo Color Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900023487. It was launched in December 2019. It has 182 units in 2 buildings: 152 homes (1 and 2 BHK) and 30 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 182 units, 106 are for sale and 76 are rehab units for existing members.

Its registered possession date is April 2030, extended by 3 years 4 months from the original December 2026. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

64 units booked out of 106 units for sale (60%). Since the July 2026 update, 27 more units have been booked, the reported concrete structure (RCC) has gone from 85% to 100% and the possession date has moved from December 2026 to April 2030.