Labdhi Seabreeze, Wadala East
Ready to move
by Labdhi Siddhivinayak Realtors LLP · Wadala East, Mumbai 400037 · Map
- Launched
- Jan 20207 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 263 of 26898%
- Buildings
- 20.6 acres
- MahaRERA complaints
- 18Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 17
- 1 BHK
- 177
- 2 BHK
- 73
- Other units
- 1
- Total units
- 268
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 263 | |
| 100% | 100% | 100% | 263 | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | 245 |
"–" means MahaRERA shows no figure for that update.
About this project
Labdhi Seabreeze by Labdhi Siddhivinayak Realtors LLP is a 268-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in January 2020 with possession due in December 2027. 263 units booked out of total 268 units. The concrete structure (RCC) is complete.
Read full summary
Labdhi Seabreeze is an SRA-sanctioned project by Labdhi Siddhivinayak Realtors LLP in Wadala East, Mumbai 400037, registered with MahaRERA as P51900023708. It was launched in January 2020. It has 268 units in 2 buildings: 267 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
263 units booked out of total 268 units (98%).