Aayesha Palace, Parel

Ready to move

by Zoeb Enterprises · Parel, Mumbai 400012 · Map

Launched
Jan 20203 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs
Concrete structure
100%Ready to move
Booked (free sale)
13 of 7916% · 83 rehab units
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 79 units

Rehab83 units for existing members

Total 162 units. Rehab units are not for sale.

Project facts

1 BHK
162
Total units
162
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2
Free-sale units
79
Rehab units
83

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%13
100%100%95%13
100%100%90%10
100%85%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aayesha Palace by Zoeb Enterprises is a 162-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in January 2020 with possession due in December 2027. 13 units booked out of 79 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aayesha Palace is a BMC-sanctioned project by Zoeb Enterprises in Parel, Mumbai 400012, registered with MahaRERA as P51900023852. It was launched in January 2020. It has 162 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 162 units, 79 are for sale and 83 are rehab units for existing members.

Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

13 units booked out of 79 units for sale (16%).