Aryavrat Project, Dadar West
by M/S Chintamani Land and Housing LLP · Dadar West, Mumbai 400028 · Map
- Launched
- Feb 20203 yrs 10 mths originally promised
- Possession (MahaRERA)
- Oct 2028Extended by 4 yrs 10 mths
- Concrete structure
- 86%Mid-construction
- Booked
- 57 of 8766% · 6 in Jul 2026
- Buildings
- 20.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 18
- 2 BHK
- 41
- 3 BHK
- 19
- 4 BHK
- 9
- Total units
- 87
- Buildings
- 2
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 86% | 0% | 57 | |
| 100% | 86% | 0% | 6 | |
| 100% | 86% | 0% | – | |
| 100% | 86% | 0% | 54 |
"–" means MahaRERA shows no figure for that update.
About this project
Aryavrat Project by M/S Chintamani Land and Housing LLP is an 87-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in February 2020 with possession due in October 2028. 57 units booked out of total 87 units. The concrete structure (RCC) is 86% complete.
Read full summary
Aryavrat Project is a BMC-sanctioned project by M/S Chintamani Land and Housing LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900024338. It was launched in February 2020. It has 87 units in 2 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2028, extended by 4 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) 86% complete, final finishes not started.
57 units booked out of total 87 units (66%). Since the July 2026 update, 51 more units have been booked and the possession date has moved from December 2024 to October 2028.