Sambhav, Malabar Hill
by Helictite Residency Private Limited · Malabar Hill, Mumbai 400006 · Map
- Launched
- Mar 20208 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 2 of 1118% · 0 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 3
- 3 BHK
- 4
- 4 BHK
- 1
- Other units
- 3
- Total units
- 11
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 2 | |
| 100% | 65% | 0% | 0 | |
| 100% | 65% | 0% | 0 | |
| 100% | 65% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sambhav by Helictite Residency Private Limited is an 11-unit BMC-sanctioned project in Malabar Hill, Mumbai 400006, launched in March 2020 with possession due in December 2028. 2 units booked out of total 11 units. The concrete structure (RCC) is complete.
Read full summary
Sambhav is a BMC-sanctioned project by Helictite Residency Private Limited in Malabar Hill, Mumbai 400006, registered with MahaRERA as P51900025024. It was launched in March 2020. It has 11 units in 1 building: 8 homes (2, 3 and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.
2 units booked out of total 11 units (18%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 65% to 100%.