Bawa Aashiyaan, Dharavi
by Kay Bee Developers Pvt Ltd · Dharavi, Mumbai 400017 · Map
- Launched
- Jul 2020First of 2 phases
- Possession (MahaRERA)
- Dec 2027 – Jun 2028Not extended
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 227
- Total units
- 227
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Bawa Aashiyaan Phase 1 Nearing possession | P51900025804 | 116 | 100% | – | |
| Bawa Aashiyaan Phase-II Nearing possession | P51900033922 | 111 | 100% | – |
Show updates by phase
Bawa Aashiyaan Phase 1 (P51900025804)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 35% | – | |
| 100% | 100% | 35% | – | |
| 100% | 100% | 35% | 91 |
"–" means MahaRERA shows no figure for that update.
Bawa Aashiyaan Phase-II (P51900033922)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | 101 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Bawa Aashiyaan by Kay Bee Developers Pvt Ltd is a 227-unit SRA-sanctioned project in Dharavi, Mumbai 400017, registered with MahaRERA in 2 phases, with possession dates from December 2027 to June 2028. The concrete structure (RCC) is complete.
Read full summary
Bawa Aashiyaan is an SRA-sanctioned project by Kay Bee Developers Pvt Ltd in Dharavi, Mumbai 400017, registered with MahaRERA as 2 phases (P51900025804, P51900033922). The first phase was launched in July 2020. Together the phases have 227 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2027 to June 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 33% complete. Both phases have their structure complete.