Nisarg Co Operative Housing Society Limited, Wadala East
Ready to move
by Cosmos Landmarks · Wadala East, Mumbai 400037 · Map
- Launched
- Jul 20202 yrs 11 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 10 mths
- Concrete structure
- 100%Ready to move
- Booked
- 77 of 7899%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 16Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 77
- Other units
- 1
- Total units
- 78
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 77 | |
| 100% | 100% | 98% | 77 | |
| 100% | 100% | 97% | 77 | |
| 100% | 100% | 90% | 77 |
"–" means MahaRERA shows no figure for that update.
About this project
Nisarg Co Operative Housing Society Limited by Cosmos Landmarks is a 78-unit BMC-sanctioned project in Wadala East, Mumbai 400037, launched in July 2020 with possession due in April 2027. 77 units booked out of total 78 units. The concrete structure (RCC) is complete.
Read full summary
Nisarg Co Operative Housing Society Limited is a BMC-sanctioned project by Cosmos Landmarks in Wadala East, Mumbai 400037, registered with MahaRERA as P51900025873. It was launched in July 2020. It has 78 units in 1 building: 77 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 3 years 10 months from the original June 2023. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
77 units booked out of total 78 units (99%).