The Aga Hall Estate, Mazgaon
by Prince Aly Khan Hospital · Mazgaon, Mumbai 400010 · Map
- Launched
- Sep 20208 yrs 9 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 97%Mid-construction
- Booked (free sale)
- 274 of 39370% · 191 rehab units
- Buildings
- 24 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale274 booked out of 393 units
Rehab191 units for existing members
Total 584 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 95
- 2 BHK
- 340
- 3 BHK
- 108
- 4 BHK
- 39
- Total units
- 584
- Buildings
- 2
- Land
- 4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 393
- Rehab units
- 191
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 9% | 274 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
The Aga Hall Estate by Prince Aly Khan Hospital is a 584-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in September 2020 with possession due in June 2029. 274 units booked out of 393 units for sale. The concrete structure (RCC) is 97% complete.
Read full summary
The Aga Hall Estate is a BMC-sanctioned project by Prince Aly Khan Hospital in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900026326. It was launched in September 2020. It has 584 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 584 units, 393 are for sale and 191 are rehab units for existing members.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 97% complete, final finishes 9% complete.
274 units booked out of 393 units for sale (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 97%.