- Launched
- Oct 20204 yrs 6 mths originally promised
- Possession (MahaRERA)
- Oct 2028Extended by 3 yrs 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 9 of 4022% · 65 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 40 units
Rehab65 units for existing members
Total 105 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 37
- 2 BHK
- 40
- 3 BHK
- 11
- Other units
- 17
- Total units
- 105
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 40
- Rehab units
- 65
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 9 | |
| 100% | 100% | 80% | 9 | |
| 100% | 100% | 0% | 5 | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Yashvi Regency by Aasma Infra-Con LLP is a 105-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in October 2020 with possession due in October 2028. 9 units booked out of 40 units for sale. The concrete structure (RCC) is complete.
Read full summary
Yashvi Regency is a BMC-sanctioned project by Aasma Infra-Con LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900026765. It was launched in October 2020. It has 105 units in 1 building: 88 homes (1, 2 and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 105 units, 40 are for sale and 65 are rehab units for existing members.
Its registered possession date is October 2028, extended by 3 years 6 months from the original April 2025. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
9 units booked out of 40 units for sale (22%).