Dosti Mezzo 22, Sion

Ready to move

by Maitri Associates · Sion, Mumbai 400022 · Map

Launched
Nov 20205 yrs 7 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 1 yr 1 mth
Concrete structure
100%Ready to move
Booked
296 of 30398% · 287 in Jul 2026
Buildings
21.4 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
166
3 BHK
137
Total units
303
Buildings
2
Land
1.4 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 92%Dec 2025: Concrete structure (RCC) 94%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 7%Dec 2025: Final finishes 27%Jul 2026: Final finishes 59%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%296
100%100%59%287
100%94%27%273
100%92%7%244

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dosti Mezzo 22 by Maitri Associates (Dosti) is a 303-unit project in Sion, Mumbai 400022, launched in November 2020 with possession due in July 2027. 296 units booked out of total 303 units. The concrete structure (RCC) is complete.

Read full summary

Dosti Mezzo 22 is a project by Maitri Associates in Sion, Mumbai 400022, registered with MahaRERA as P51900026976. It was launched in November 2020. It has 303 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 1 year 1 month from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

296 units booked out of total 303 units (98%). Since the July 2026 update, 9 more units have been booked and the possession date has moved from June 2026 to July 2027.

Dosti's track record in Mumbai

MahaRERA projects registered 2018–2021 in Mumbai

Projects registered with MahaRERA6
Total units across these projects1,608
Completed without extending the possession date5
Completed after an extension0
Lapsed0
Under construction1
Possession date extended on the builder's application1
Typical time from launch to 100% structure4 years 4 months
MahaRERA complaints (filed by or against the builder), all Dosti projects4 (3 of 6 projects)

See all Dosti projects →