Shanti Harbour Crest, Sewri
by Ojus Developers · Sewri, Mumbai 400015 · Map
- Launched
- Nov 20203 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jun 2028Extended by 4 yrs 6 mths
- Concrete structure
- 45%Mid-construction
- Booked
- 34 of 3987%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 39
- Total units
- 39
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 34 | |
| 100% | 19% | 0% | 34 | |
| 100% | 19% | 0% | 34 | |
| 100% | 19% | 0% | 33 |
"–" means MahaRERA shows no figure for that update.
About this project
Shanti Harbour Crest by Ojus Developers is a 39-unit SRA-sanctioned project in Sewri, Mumbai 400015, launched in November 2020 with possession due in June 2028. 34 units booked out of total 39 units. The concrete structure (RCC) is 45% complete.
Read full summary
Shanti Harbour Crest is an SRA-sanctioned project by Ojus Developers in Sewri, Mumbai 400015, registered with MahaRERA as P51900027180. It was launched in November 2020. It has 39 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2028, extended by 4 years 6 months from the original December 2023. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
34 units booked out of total 39 units (87%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 19% to 45% and the possession date has moved from June 2026 to June 2028.