Skip to main content

Hussaini Park, Mazgaon

by Grace Enterprises · Mazgaon, Mumbai 400010 · Map

Launched
Feb 20214 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 2 yrs
Concrete structure
100%Nearing possession
Booked
70 of 10269% · 71 in Jul 2026
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
51
2 BHK
50
3 BHK
1
Total units
102
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%70
100%91%0%71
100%87%0%62
100%87%0%47

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Hussaini Park by Grace Enterprises is a 102-unit project in Mazgaon, Mumbai 400010, launched in February 2021 with possession due in June 2027. 70 units booked out of total 102 units. The concrete structure (RCC) is complete.

Read full summary

Hussaini Park is a project by Grace Enterprises in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900028273. It was launched in February 2021. It has 102 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 2 years from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

70 units booked out of total 102 units (69%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 91% to 100% and the possession date has moved from June 2026 to June 2027.