Infinity Residences, Kalachowki
by Infinity Associates · Kalachowki, Mumbai 400033 · Map
- Launched
- Sep 20217 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 71%Mid-construction
- Booked
- 147 of 21369%
- Buildings
- 11.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 213
- Total units
- 213
- Buildings
- 1
- Land
- 1.6 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 71% | 0% | 147 | |
| 100% | 71% | 0% | – | |
| 100% | 71% | 0% | – | |
| 100% | 100% | 0% | 147 |
"–" means MahaRERA shows no figure for that update.
About this project
Infinity Residences by Infinity Associates is a 213-unit SRA-sanctioned project in Kalachowki, Mumbai 400033, launched in September 2021 with possession due in December 2028. 147 units booked out of total 213 units. The concrete structure (RCC) is 71% complete.
Read full summary
Infinity Residences is an SRA-sanctioned project by Infinity Associates in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900030602. It was launched in September 2021. It has 213 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 71% complete, final finishes not started.
147 units booked out of total 213 units (69%).