by Twenty Five South Reality Limited · Prabhadevi, Mumbai 400025 · Map

Launched
Sep 20219 yrs 3 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
85%Mid-construction
Booked
25 of 2986% · 24 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
23
5+ BHK
6
Total units
29
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 65%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Final finishes 95%Concrete structure (RCC) 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%95%25
100%80%95%24
100%65%95%22
100%25%0%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

TwentyFive South -Tower C by Twenty Five South Reality Limited is a 29-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, launched in September 2021 with possession due in December 2030. 25 units booked out of total 29 units. The concrete structure (RCC) is 85% complete.

Read full summary

TwentyFive South -Tower C is a BMC-sanctioned project by Twenty Five South Reality Limited in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900030729. It was launched in September 2021. It has 29 units in 1 building, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 95% complete.

25 units booked out of total 29 units (86%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 80% to 85%.