- Launched
- Oct 2021First of 2 phases
- Possession (MahaRERA)
- Dec 2026Extended in both phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 361 of 57263%
- Buildings
- 44.5 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 2
- 2 BHK
- 471
- 3 BHK
- 84
- 4 BHK
- 6
- 5+ BHK
- 1
- Other units
- 8
- Total units
- 572
- Buildings
- 4
- Land
- 4.5 acres
- Phases
- 2
- MahaRERA complaints
- 5
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| The Views Ready to move | P51900031165 | 282 | 100% | 74% | |
| The Views II Ready to move | P51900033194 | 282 | 100% | 52% |
Show updates by phase
The Views (P51900031165)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 211 | |
| 100% | 100% | 100% | 211 | |
| 100% | 100% | 5% | 200 | |
| 100% | 98% | 0% | 189 |
"–" means MahaRERA shows no figure for that update.
The Views II (P51900033194)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 150 | |
| 100% | 100% | 100% | 150 | |
| 100% | 100% | 0% | 123 | |
| 100% | 100% | 0% | 95 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
The Views by Agnel Developers is a 572-unit project in Ghatkopar East, Mumbai 400075, registered with MahaRERA in 2 phases, with possession due in December 2026. 361 units booked out of total 572 units. The concrete structure (RCC) is complete.
Read full summary
The Views is a project by Agnel Developers in Ghatkopar East, Mumbai 400075, registered with MahaRERA as 2 phases (P51900031165, P51900033194). The first phase was launched in October 2021. Together the phases have 572 units in 4 buildings: 564 homes (1, 2, 3, 4 and 5+ BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is December 2026; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 100% complete. Both phases have their structure complete.
361 units booked out of total 572 units (63%).