by Aditya Birla Real Estate Limited · Worli, Mumbai 400030 · Map

Launched
Nov 2021First of 2 phases
Possession (MahaRERA)
Mar 2028 – Mar 2029Not extended
Concrete structure
74%Weighted across 2 phases
Booked
520 of 56293% · 509 in Jul 2026
Buildings
20.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
170
3 BHK
177
4 BHK
99
5+ BHK
115
Total units
562
Buildings
2
Land
0.5 acres
Phases
2
MahaRERA complaints
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Birla Niyaara Phase-1
Nearing possession
P51900031916414100%97%
Birla Niyaara Phase-2
Early stage
P519000544551480%80%
Show updates by phase

Birla Niyaara Phase-1 (P51900031916)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%6%401
100%100%0%400
100%82%0%400
100%36%0%388

"–" means MahaRERA shows no figure for that update.

Birla Niyaara Phase-2 (P51900054455)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%119
100%0%0%109
100%0%0%109
100%0%0%69

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)74%
Finishes, lifts and services4%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 27%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 74%Oct 2026: Concrete structure (RCC) 74%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 4%Excavation 100%Concrete structure (RCC) 74%Final finishes 4%

How to read construction stages

About this project

Birla Niyaara by Aditya Birla Real Estate Limited is a 562-unit BMC-sanctioned project in Worli, Mumbai 400030, registered with MahaRERA in 2 phases, with possession dates from March 2028 to March 2029. 520 units booked out of total 562 units. The concrete structure (RCC) is 74% complete.

Read full summary

Birla Niyaara is a BMC-sanctioned project by Aditya Birla Real Estate Limited in Worli, Mumbai 400030, registered with MahaRERA as 2 phases (P51900031916, P51900054455). The first phase was launched in November 2021. Together the phases have 562 units in 2 buildings, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from March 2028 to March 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 74% complete and final finishes 4% complete. Neither phase has its structure complete.

520 units booked out of total 562 units (93%). Since the July 2026 update, 11 more units have been booked.