Avenue 15, Sewri
by Ramesh Barrel Supplying Co · Sewri, Mumbai 400015 · Map
- Launched
- Dec 20213 yrs 3 mths originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 1 yr 10 mths
- Concrete structure
- 97%Mid-construction
- Booked
- 62 of 12749% · 54 in Jul 2026
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 82
- 2 BHK
- 43
- Other units
- 1
- Total units
- 127
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 60% | 62 | |
| 100% | 97% | 60% | 54 | |
| 100% | 95% | 50% | 33 | |
| 100% | 45% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
Avenue 15 by Ramesh Barrel Supplying Co is a 127-unit BMC-sanctioned project in Sewri, Mumbai 400015, launched in December 2021 with possession due in January 2027. 62 units booked out of total 127 units. The concrete structure (RCC) is 97% complete.
Read full summary
Avenue 15 is a BMC-sanctioned project by Ramesh Barrel Supplying Co in Sewri, Mumbai 400015, registered with MahaRERA as P51900032165. It was launched in December 2021. It has 127 units in 1 building: 126 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is January 2027, extended by 1 year 10 months from the original March 2025. Construction: excavation complete, structure (RCC) 97% complete, final finishes 60% complete.
62 units booked out of total 127 units (49%). Since the July 2026 update, 8 more units have been booked and the possession date has moved from March 2026 to January 2027.