Aryan View, Lower Parel

by Aryan Associate · Lower Parel, Mumbai 400013 · Map

Launched
Dec 20212 yrs originally promised
Possession (MahaRERA)
Oct 2028Extended by 4 yrs 10 mths
Concrete structure
35%Mid-construction
Booked (free sale)
14 of 1688% · 15 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 16 units

Rehab15 units for existing members

Total 31 units. Rehab units are not for sale.

Project facts

1 RK
8
1 BHK
17
Other units
6
Total units
31
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 13%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%14
100%35%0%–
100%35%0%–
100%13%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aryan View by Aryan Associate is a 31-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in December 2021 with possession due in October 2028. 14 units booked out of 16 units for sale. The concrete structure (RCC) is 35% complete.

Read full summary

Aryan View is a BMC-sanctioned project by Aryan Associate in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900032191. It was launched in December 2021. It has 31 units in 1 building: 25 homes (1 RK and 1 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 16 are for sale and 15 are rehab units for existing members.

Its registered possession date is October 2028, extended by 4 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

14 units booked out of 16 units for sale (88%). Since the July 2026 update, the possession date has moved from December 2024 to October 2028.