Aryan View, Lower Parel
by Aryan Associate · Lower Parel, Mumbai 400013 · Map
- Launched
- Dec 20212 yrs originally promised
- Possession (MahaRERA)
- Oct 2028Extended by 4 yrs 10 mths
- Concrete structure
- 35%Mid-construction
- Booked (free sale)
- 14 of 1688% · 15 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale14 booked out of 16 units
Rehab15 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 RK
- 8
- 1 BHK
- 17
- Other units
- 6
- Total units
- 31
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 14 | |
| 100% | 35% | 0% | – | |
| 100% | 35% | 0% | – | |
| 100% | 13% | 0% | 15 |
"–" means MahaRERA shows no figure for that update.
About this project
Aryan View by Aryan Associate is a 31-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in December 2021 with possession due in October 2028. 14 units booked out of 16 units for sale. The concrete structure (RCC) is 35% complete.
Read full summary
Aryan View is a BMC-sanctioned project by Aryan Associate in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900032191. It was launched in December 2021. It has 31 units in 1 building: 25 homes (1 RK and 1 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 16 are for sale and 15 are rehab units for existing members.
Its registered possession date is October 2028, extended by 4 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.
14 units booked out of 16 units for sale (88%). Since the July 2026 update, the possession date has moved from December 2024 to October 2028.