Moraj Opulence, Mahim

by Moraj Ahn Developers LLP · Mahim, Mumbai 400016 · Map

Launched
Dec 20215 yrs originally promised
Possession (MahaRERA)
Dec 2029Extended by 3 yrs
Concrete structure
75%Mid-construction
Booked
23 of 4551% · 20 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
44
Other units
1
Total units
45
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 53%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%23
100%53%0%20
100%0%0%18
100%5%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Moraj Opulence by Moraj Ahn Developers LLP is a 45-unit SRA-sanctioned project in Mahim, Mumbai 400016, launched in December 2021 with possession due in December 2029. 23 units booked out of total 45 units. The concrete structure (RCC) is 75% complete.

Read full summary

Moraj Opulence is an SRA-sanctioned project by Moraj Ahn Developers LLP in Mahim, Mumbai 400016, registered with MahaRERA as P51900032370. It was launched in December 2021. It has 45 units in 1 building: 44 homes (3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 3 years from the original December 2026. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.

23 units booked out of total 45 units (51%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 53% to 75%.