Inara, Chinchbunder
by M/S S Square Construction · Chinchbunder, Mumbai 400009 · Map
- Launched
- Jan 202211 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 4 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 28 of 3678%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale28 booked out of 36 units
Land-owner share24 units, not for sale
Total 60 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 40
- 2 BHK
- 20
- Total units
- 60
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 36
- Land-owner share (not for sale)
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 28 | |
| 100% | 100% | 80% | 28 | |
| 100% | 100% | 80% | 24 | |
| 100% | 100% | 80% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Inara by M/S S Square Construction is a 60-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in January 2022 with possession due in April 2027. 28 units booked out of 36 units for sale. The concrete structure (RCC) is complete.
Read full summary
Inara is a BMC-sanctioned project by M/S S Square Construction in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900032522. It was launched in January 2022. It has 60 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 60 units, 36 are for sale and 24 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
28 units booked out of 36 units for sale (78%).