by M/S S Square Construction · Chinchbunder, Mumbai 400009 · Map

Launched
Jan 202211 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 4 yrs 4 mths
Concrete structure
100%Nearing possession
Booked (free sale)
28 of 3678%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale28 booked out of 36 units

Land-owner share24 units, not for sale

Total 60 units. Land-owner units are not for sale.

Project facts

1 BHK
40
2 BHK
20
Total units
60
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
36
Land-owner share (not for sale)
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%28
100%100%80%28
100%100%80%24
100%100%80%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Inara by M/S S Square Construction is a 60-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in January 2022 with possession due in April 2027. 28 units booked out of 36 units for sale. The concrete structure (RCC) is complete.

Read full summary

Inara is a BMC-sanctioned project by M/S S Square Construction in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900032522. It was launched in January 2022. It has 60 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 60 units, 36 are for sale and 24 are the land-owner's share, not for sale.

Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

28 units booked out of 36 units for sale (78%).