The Edge, Parel
by Tejukaya Corp Private Limited · Parel, Mumbai 400012 · Map
- Launched
- Jan 20226 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2030Extended by 2 yrs
- Concrete structure
- 25%Mid-construction
- Booked
- 240 of 37963% · 169 in Jul 2026
- Buildings
- 32.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 148
- 3 BHK
- 139
- 4 BHK
- 76
- Other units
- 16
- Total units
- 379
- Buildings
- 3
- Land
- 2.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 240 | |
| 47% | 0% | 0% | 169 | |
| 70% | 11% | 0% | 169 | |
| 47% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
The Edge by Tejukaya Corp Private Limited is a 379-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in January 2022 with possession due in December 2030. 240 units booked out of total 379 units. The concrete structure (RCC) is 25% complete.
Read full summary
The Edge is a BMC-sanctioned project by Tejukaya Corp Private Limited in Parel, Mumbai 400012, registered with MahaRERA as P51900032613. It was launched in January 2022. It has 379 units in 3 buildings: 363 homes (2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, extended by 2 years from the original December 2028. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.
240 units booked out of total 379 units (63%). Since the July 2026 update, 71 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 25%.