Self-Redevelopment of Jeevan Smriti CHS Ltd, Goregaon East

by Jeevan Smriti Co-Operative Housing Society Ltd · Goregaon East, Mumbai 400063 · Map

Launched
Feb 20222 yrs 10 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 2 yrs 7 mths
Concrete structure
100%Nearing possession
Booked (free sale)
9 of 9100% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 9 units

Rehab12 units for existing members

Total 21 units. Rehab units are not for sale.

Project facts

1 BHK
7
2 BHK
13
3 BHK
1
Total units
21
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 25%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%9
100%100%75%–
100%100%25%–
100%100%20%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400063

Projects with 10–50 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 5 mths
Possession date extendedBy 2 yrs 7 mths3 of 5
Possession date (MahaRERA)Jul 2027Nov 2026
Concrete structure (RCC)100%75%
Units booked (free sale)100%68%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Self-Redevelopment of Jeevan Smriti CHS Ltd by Jeevan Smriti Co-Operative Housing Society Ltd is a 21-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in February 2022 with possession due in July 2027. 9 units booked out of 9 units for sale. The concrete structure (RCC) is complete.

Read full summary

Self-Redevelopment of Jeevan Smriti CHS Ltd is a BMC-sanctioned project by Jeevan Smriti Co-Operative Housing Society Ltd in Goregaon East, Mumbai 400063, registered with MahaRERA as P51900033146. It was launched in February 2022. It has 21 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 9 are for sale and 12 are rehab units for existing members.

Its registered possession date is July 2027, extended by 2 years 7 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

9 units booked out of 9 units for sale (100%). Since the July 2026 update, the possession date has moved from December 2025 to July 2027.