by Swayam Realtors & Traders LLP · Mahalaxmi, Mumbai 400011 · Map

Launched
Feb 20224 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2030Extended by 4 yrs 6 mths
Concrete structure
35%Mid-construction
Booked
396 of 396100%
Buildings
18.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
184
3 BHK
212
Total units
396
Buildings
1
Land
8.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 3%Jul 2026: Concrete structure (RCC) 27%Oct 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%35%0%396
70%27%0%396
70%3%0%294
100%50%0%88

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Montesouth Zermatt-1 by Swayam Realtors & Traders LLP is a 396-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in February 2022 with possession due in December 2030. 396 units booked out of total 396 units. The concrete structure (RCC) is 35% complete.

Read full summary

Montesouth Zermatt-1 is a BMC-sanctioned project by Swayam Realtors & Traders LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900033347. It was launched in February 2022. It has 396 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, extended by 4 years 6 months from the original June 2026. Construction: excavation 70% complete, structure (RCC) 35% complete, final finishes not started.

396 units booked out of total 396 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 27% to 35%.