The Auro, Lower Parel

Ready to move

by Alamdar Infrastructure Pvt Ltd · Lower Parel, Mumbai 400013 · Map

Launched
Mar 20225 yrs 8 mths promised
Possession (MahaRERA)
Nov 2027Not extended
Concrete structure
100%Ready to move
Booked
21 of 2488%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
22
3 BHK
2
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 95%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%21
100%100%95%15
100%100%25%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Auro by Alamdar Infrastructure Pvt Ltd is a 24-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in March 2022 with possession due in November 2027. 21 units booked out of total 24 units. The concrete structure (RCC) is complete.

Read full summary

The Auro is a BMC-sanctioned project by Alamdar Infrastructure Pvt Ltd in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900033823. It was launched in March 2022. It has 24 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

21 units booked out of total 24 units (88%).