The Auro, Lower Parel
Ready to move
by Alamdar Infrastructure Pvt Ltd · Lower Parel, Mumbai 400013 · Map
- Launched
- Mar 20225 yrs 8 mths promised
- Possession (MahaRERA)
- Nov 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 21 of 2488%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 22
- 3 BHK
- 2
- Total units
- 24
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 21 | |
| 100% | 100% | 95% | 15 | |
| 100% | 100% | 25% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
The Auro by Alamdar Infrastructure Pvt Ltd is a 24-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in March 2022 with possession due in November 2027. 21 units booked out of total 24 units. The concrete structure (RCC) is complete.
Read full summary
The Auro is a BMC-sanctioned project by Alamdar Infrastructure Pvt Ltd in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900033823. It was launched in March 2022. It has 24 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
21 units booked out of total 24 units (88%).