Nexsa Sky Vista, Mumbai Central
by D.K. Realtors & Developers Limited · Mumbai Central, Mumbai 400008 · Map
- Launched
- Mar 20224 yrs 8 mths originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 7 mths
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 33 of 13524% · 178 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 135 units
Rehab178 units for existing members
Total 313 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 242
- 2 BHK
- 20
- Other units
- 50
- Total units
- 313
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 135
- Rehab units
- 178
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 33 | |
| 50% | 35% | 0% | 4 | |
| 50% | 35% | 0% | – | |
| 100% | 12% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Nexsa Sky Vista by D.K. Realtors & Developers Limited is a 313-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in March 2022 with possession due in June 2027. 33 units booked out of 135 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Nexsa Sky Vista is a BMC-sanctioned project by D.K. Realtors & Developers Limited in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900033907. It was launched in March 2022. It has 313 units in 1 building: 263 homes (1 RK, 1 BHK and 2 BHK) and 50 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 313 units, 135 are for sale and 178 are rehab units for existing members.
Its registered possession date is June 2027, extended by 7 months from the original November 2026. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
33 units booked out of 135 units for sale (24%). Since the July 2026 update, 29 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 70%.