Shanti Tower, Prabhadevi
Ready to move
by Shanti Prakash Realty & Infrastructure LLP · Prabhadevi, Mumbai 400025 · Map
- Launched
- Mar 20228 yrs 1 mth promised
- Possession (MahaRERA)
- Apr 2030Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 21 of 7528%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 61
- Other units
- 14
- Total units
- 75
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 21 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 70% | – | |
| 80% | 70% | 0% | 21 |
"–" means MahaRERA shows no figure for that update.
About this project
Shanti Tower by Shanti Prakash Realty & Infrastructure LLP is a 75-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, launched in March 2022 with possession due in April 2030. 21 units booked out of total 75 units. The concrete structure (RCC) is complete.
Read full summary
Shanti Tower is a BMC-sanctioned project by Shanti Prakash Realty & Infrastructure LLP in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900033948. It was launched in March 2022. It has 75 units in 1 building: 61 homes (1 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2030, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
21 units booked out of total 75 units (28%).