Nine Reflex, Dadar East
by Reflex Projects LLP · Dadar East, Mumbai 400014 · Map
- Launched
- Mar 20222 yrs 9 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 4 mths
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 7 of 2924% · 42 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 29 units
Rehab42 units for existing members
Total 71 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 59
- Other units
- 12
- Total units
- 71
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 42
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 10% | 7 | |
| 100% | 95% | 10% | 7 | |
| 100% | 86% | 0% | – | |
| 100% | 45% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Nine Reflex by Reflex Projects LLP is a 71-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in March 2022 with possession due in April 2027. 7 units booked out of 29 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Nine Reflex is a BMC-sanctioned project by Reflex Projects LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900034207. It was launched in March 2022. It has 71 units in 1 building: 59 homes (2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 29 are for sale and 42 are rehab units for existing members.
Its registered possession date is April 2027, extended by 2 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) 95% complete, final finishes 10% complete.
7 units booked out of 29 units for sale (24%).