One India Heights, Mumbai Central

by Oneindia Construction LLP · Mumbai Central, Mumbai 400008 · Map

Launched
Apr 20222 yrs originally promised
Possession (MahaRERA)
Apr 2029Extended by 5 yrs
Concrete structure
75%Mid-construction
Booked (free sale)
20 of 3067% · 42 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 30 units

Rehab42 units for existing members

Total 72 units. Rehab units are not for sale.

Project facts

1 BHK
61
Other units
11
Total units
72
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
42

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services37%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 37%Oct 2026: Final finishes 37%Excavation 100%Concrete structure (RCC) 75%Final finishes 37%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%37%20
100%75%37%20
100%75%25%20
100%70%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400008

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs4 yrs 10 mths
Possession date extendedBy 5 yrs1 of 3
Possession date (MahaRERA)Apr 2029Mar 2027
Concrete structure (RCC)75%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

One India Heights by Oneindia Construction LLP is a 72-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in April 2022 with possession due in April 2029. 20 units booked out of 30 units for sale. The concrete structure (RCC) is 75% complete.

Read full summary

One India Heights is a BMC-sanctioned project by Oneindia Construction LLP in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900034445. It was launched in April 2022. It has 72 units in 1 building: 61 homes (1 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 30 are for sale and 42 are rehab units for existing members.

Its registered possession date is April 2029, extended by 5 years from the original April 2024. Construction: excavation complete, structure (RCC) 75% complete, final finishes 37% complete.

20 units booked out of 30 units for sale (67%).