Gundecha-Kbk-Magnum Phase I, Parel

by GundechaConstructionPvtLtd · Parel, Mumbai 400012 · Map

Launched
Apr 20224 yrs 11 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
85%Mid-construction
Booked
102 of 17060%
Buildings
12.9 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
110
3 BHK
60
Total units
170
Buildings
1
Land
2.9 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%102
100%70%0%–
100%70%0%–
100%50%0%73

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Gundecha-Kbk-Magnum Phase I by GundechaConstructionPvtLtd is a 170-unit SRA-sanctioned project in Parel, Mumbai 400012, launched in April 2022 with possession due in March 2027. 102 units booked out of total 170 units. The concrete structure (RCC) is 85% complete.

Read full summary

Gundecha-Kbk-Magnum Phase I is an SRA-sanctioned project by GundechaConstructionPvtLtd in Parel, Mumbai 400012, registered with MahaRERA as P51900034493. It was launched in April 2022. It has 170 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

102 units booked out of total 170 units (60%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 70% to 85%.