Dharti Heights, Parel

by Om Shanti Housing · Parel, Mumbai 400012 · Map

Launched
May 20224 yrs 7 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
–
Buildings
11 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
40
3 BHK
37
Total units
77
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 70%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%–
100%100%70%–
100%100%70%–
100%100%70%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dharti Heights by Om Shanti Housing is a 77-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in May 2022 with possession due in December 2026. The concrete structure (RCC) is complete.

Read full summary

Dharti Heights is a BMC-sanctioned project by Om Shanti Housing in Parel, Mumbai 400012, registered with MahaRERA as P51900035208. It was launched in May 2022. It has 77 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.