Dharti Heights, Parel
by Om Shanti Housing · Parel, Mumbai 400012 · Map
- Launched
- May 20224 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 11 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 40
- 3 BHK
- 37
- Total units
- 77
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Dharti Heights by Om Shanti Housing is a 77-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in May 2022 with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
Dharti Heights is a BMC-sanctioned project by Om Shanti Housing in Parel, Mumbai 400012, registered with MahaRERA as P51900035208. It was launched in May 2022. It has 77 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.