Nakoda Mehta Sunshine Heights A And C Wings, Girgaon
by Chandulal Joravarmalji Mehta · Girgaon, Mumbai 400004 · Map
- Launched
- Jun 20224 yrs 10 mths promised
- Possession (MahaRERA)
- Apr 2027Not extended
- Concrete structure
- 86%Mid-construction
- Booked (free sale)
- 60 of 11552%
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale60 booked out of 115 units
Land-owner share196 units, not for sale
Total 311 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 62
- 2 BHK
- 105
- 3 BHK
- 91
- Other units
- 53
- Total units
- 311
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 115
- Land-owner share (not for sale)
- 196
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 86% | 0% | 60 | |
| 100% | 48% | 0% | 0 | |
| 100% | 48% | 0% | – | |
| 100% | 23% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Nakoda Mehta Sunshine Heights A And C Wings by Chandulal Joravarmalji Mehta is a 311-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in June 2022 with possession due in April 2027. 60 units booked out of 115 units for sale. The concrete structure (RCC) is 86% complete.
Read full summary
Nakoda Mehta Sunshine Heights A And C Wings is a BMC-sanctioned project by Chandulal Joravarmalji Mehta in Girgaon, Mumbai 400004, registered with MahaRERA as P51900045988. It was launched in June 2022. It has 311 units in 1 building: 258 homes (1, 2 and 3 BHK) and 53 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 311 units, 115 are for sale and 196 are the land-owner's share, not for sale.
Its registered possession date is April 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 86% complete, final finishes not started.
60 units booked out of 115 units for sale (52%). Since the July 2026 update, 60 more units have been booked and the reported concrete structure (RCC) has gone from 48% to 86%.