Sanghvi Parsssva Eternity, Girgaon
by Sanghvi Parsssva Enterprise LLP · Girgaon, Mumbai 400004 · Map
- Launched
- Jun 20224 yrs originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 2 yrs 10 mths
- Concrete structure
- 35%Mid-construction
- Booked
- 29 of 5157% · 26 in Jul 2026
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 20
- 3 BHK
- 29
- Other units
- 2
- Total units
- 51
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 3% | 29 | |
| 100% | 19% | 0% | 26 | |
| 100% | 19% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sanghvi Parsssva Eternity by Sanghvi Parsssva Enterprise LLP is a 51-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in June 2022 with possession due in April 2029. 29 units booked out of total 51 units. The concrete structure (RCC) is 35% complete.
Read full summary
Sanghvi Parsssva Eternity is a BMC-sanctioned project by Sanghvi Parsssva Enterprise LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900046223. It was launched in June 2022. It has 51 units in 2 buildings: 49 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2029, extended by 2 years 10 months from the original June 2026. Construction: excavation complete, structure (RCC) 35% complete, final finishes 3% complete.
29 units booked out of total 51 units (57%). Since the July 2026 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 19% to 35% and the possession date has moved from June 2026 to April 2029.