Island Cove, Mahim

by LH Residential Housing Private Limited · Mahim, Mumbai 400016 · Map

Launched
Jun 20226 yrs 2 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 4 mths
Concrete structure
45%Mid-construction
Booked
493 of 52394% · 470 in Jul 2026
Buildings
21.6 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
256
3 BHK
242
Other units
25
Total units
523
Buildings
2
Land
1.6 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 16%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%493
100%16%0%470
100%0%0%442
0%0%0%331

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Island Cove by LH Residential Housing Private Limited is a 523-unit SRA-sanctioned project in Mahim, Mumbai 400016, launched in June 2022 with possession due in December 2028. 493 units booked out of total 523 units. The concrete structure (RCC) is 45% complete.

Read full summary

Island Cove is an SRA-sanctioned project by LH Residential Housing Private Limited in Mahim, Mumbai 400016, registered with MahaRERA as P51900046369. It was launched in June 2022. It has 523 units in 2 buildings: 498 homes (2 and 3 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 4 months from the original August 2028. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

493 units booked out of total 523 units (94%). Since the July 2026 update, 23 more units have been booked and the reported concrete structure (RCC) has gone from 16% to 45%.