Sanjana Heights, Kemps Corner

by Safeway Projects Pvt Ltd · Kemps Corner, Mumbai 400036 · Map

Launched
Aug 20224 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
32%Mid-construction
Booked
0 of 120%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
1
3 BHK
11
Total units
12
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)32%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 17%Jul 2026: Concrete structure (RCC) 17%Oct 2026: Concrete structure (RCC) 32%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 32%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%32%0%0
100%17%0%0
100%17%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sanjana Heights by Safeway Projects Pvt Ltd is a 12-unit BMC-sanctioned project in Kemps Corner, Mumbai 400036, launched in August 2022 with possession due in December 2026. 0 units booked out of total 12 units. The concrete structure (RCC) is 32% complete.

Read full summary

Sanjana Heights is a BMC-sanctioned project by Safeway Projects Pvt Ltd in Kemps Corner, Mumbai 400036, registered with MahaRERA as P51900046485. It was launched in August 2022. It has 12 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 32% complete, final finishes not started.

0 units booked out of total 12 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 17% to 32%.