232 Dhuleva, Girgaon

by Magnum Landcon LLP · Girgaon, Mumbai 400004 · Map

Launched
Aug 20225 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
50%Mid-construction
Booked
44 of 12236%
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
64
3 BHK
34
4 BHK
6
5+ BHK
16
Other units
2
Total units
122
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%44
100%50%0%44
100%50%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

232 Dhuleva by Magnum Landcon LLP is a 122-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2022 with possession due in December 2027. 44 units booked out of total 122 units. The concrete structure (RCC) is 50% complete.

Read full summary

232 Dhuleva is a BMC-sanctioned project by Magnum Landcon LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900046593. It was launched in August 2022. It has 122 units in 1 building: 120 homes (2, 3, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

44 units booked out of total 122 units (36%).