Skip to main content

Earth Enclave, Girgaon

by Earth Graphics · Girgaon, Mumbai 400004 · Map

Launched
Sep 20225 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
93%Mid-construction
Booked (free sale)
47 of 8158% · 214 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale47 booked out of 81 units

Rehab214 units for existing members

Total 295 units. Rehab units are not for sale.

Project facts

1 BHK
56
2 BHK
149
3 BHK
27
4 BHK
8
Other units
55
Total units
295
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
81
Rehab units
214

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services63%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 62%Dec 2025: Concrete structure (RCC) 62%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 63%Excavation 100%Concrete structure (RCC) 93%Final finishes 63%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%63%47
100%100%20%45
100%62%0%–
100%62%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Earth Enclave by Earth Graphics is a 295-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in September 2022 with possession due in December 2027. 47 units booked out of 81 units for sale. The concrete structure (RCC) is 93% complete.

Read full summary

Earth Enclave is a BMC-sanctioned project by Earth Graphics in Girgaon, Mumbai 400004, registered with MahaRERA as P51900046831. It was launched in September 2022. It has 295 units in 2 buildings: 240 homes (1, 2, 3 and 4 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 295 units, 81 are for sale and 214 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 93% complete, final finishes 63% complete.

47 units booked out of 81 units for sale (58%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 100% to 93%.