Skip to main content

Adi Darsshan, Lower Parel

by Adi Realtors · Lower Parel, Mumbai 400013 · Map

Launched
Oct 20224 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
0%Early stage
Booked (free sale)
78 of 8790% · 5 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale78 booked out of 87 units

Rehab5 units for existing members

Total 92 units. Rehab units are not for sale.

Project facts

1 BHK
87
Other units
5
Total units
92
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
87
Rehab units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation5%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 5%Dec 2025: Excavation 5%Jul 2026: Excavation 5%Oct 2026: Excavation 5%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 5%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
5%0%0%78
5%0%0%–
5%0%0%–
5%0%0%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Adi Darsshan by Adi Realtors is a 92-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in October 2022 with possession due in December 2026. 78 units booked out of 87 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Adi Darsshan is a BMC-sanctioned project by Adi Realtors in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900047289. It was launched in October 2022. It has 92 units in 1 building: 87 homes (1 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 92 units, 87 are for sale and 5 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 5% complete, structure (RCC) not started, final finishes not started.

78 units booked out of 87 units for sale (90%).