- Launched
- Oct 20222 yrs 11 mths originally promised
- Possession (MahaRERA)
- Aug 2026Extended by 11 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 5 of 956% · 16 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 9 units
Rehab16 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 5
- 2 BHK
- 7
- 3 BHK
- 10
- Other units
- 2
- Total units
- 25
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 5 | |
| 100% | 100% | 100% | 3 | |
| 100% | 100% | 50% | 3 | |
| 95% | 95% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400007
Projects with 10–50 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 4 yrs 1 mth |
| Possession date extended | By 11 mths | 0 of 6 |
| Possession date (MahaRERA) | Aug 2026 | Nov 2027 |
| Concrete structure (RCC) | 100% | 65% |
| Units booked (free sale) | 56% | 29% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Central Park, Grant Road
- Servai Tower, Grant Road
- Sarah Heights, Grant Road
- Shapoorji Pallonji The Odyssey 1, Grant Road
- Novelty Grandeur, Grant Road
- Krypton Crown, Grant Road
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Central Park | September 2022 | Jul 2028 | 100% | – |
| Servai Tower | February 2023 | December 2026 | 70% | 5 units booked out of total 17 units |
| Sarah Heights | February 2023 | December 2023 | 90% | – |
| Shapoorji Pallonji The Odyssey 1 | May 2023 | August 2031 | 0% | 24 units booked out of 45 units for sale |
| Novelty Grandeur | May 2023 | March 2030 | 0% | 5 units booked out of total 45 units |
| Krypton Crown | August 2023 | March 2027 | 60% | – |
About this project
Sugan Heights by Gulabdevi Jain & Others is a 25-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in October 2022 with possession due in August 2026. 5 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sugan Heights is a BMC-sanctioned project by Gulabdevi Jain & Others in Grant Road, Mumbai 400007, registered with MahaRERA as P51900047379. It was launched in October 2022. It has 25 units in 1 building: 23 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 9 are for sale and 16 are rehab units for existing members.
Possession was due in August 2026, after an extension of 11 months from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
5 units booked out of 9 units for sale (56%). Since the July 2026 update, 2 more units have been booked.