by Oriental Contractors Private Limited · Matunga, Mumbai 400019 · Map

Launched
Nov 20223 yrs 10 mths promised
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
0%Early stage
Booked (free sale)
30 of 3586% · 60 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale30 booked out of 35 units

Rehab60 units for existing members

Land-owner share10 units, not for sale

Total 105 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
58
2 BHK
18
3 BHK
14
5+ BHK
2
Other units
13
Total units
105
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
35
Rehab units
60
Land-owner share (not for sale)
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%30
0%0%0%30
0%0%0%30
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400019

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths5 yrs 6 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Sep 2026Dec 2027
Concrete structure (RCC)0%100%
Units booked (free sale)86%62%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Balkrishna Hills by Oriental Contractors Private Limited is a 105-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in November 2022 with possession due in September 2026. 30 units booked out of 35 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Balkrishna Hills is a BMC-sanctioned project by Oriental Contractors Private Limited in Matunga, Mumbai 400019, registered with MahaRERA as P51900047522. It was launched in November 2022. It has 105 units in 1 building: 92 homes (1, 2, 3 and 5+ BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 105 units, 35 are for sale, 60 are rehab units for existing members and 10 are the land-owner's share, not for sale.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.

30 units booked out of 35 units for sale (86%).