Bliss, Cumballa Hill
by M/s. Euphrosyne Infrastructure (OPC) Pvt Ltd · Cumballa Hill, Mumbai 400026 · Map
- Launched
- Dec 20222 yrs originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 3 of 838% · 5 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 8 units
Rehab5 units for existing members
Total 13 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 1
- 4 BHK
- 2
- 5+ BHK
- 3
- Other units
- 6
- Total units
- 13
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 5
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 3 | |
| 100% | 100% | 50% | 3 | |
| 100% | 100% | 30% | 3 | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Bliss by M/s. Euphrosyne Infrastructure (OPC) Pvt Ltd is a 13-unit BMC-sanctioned project in Cumballa Hill, Mumbai 400026, launched in December 2022 with possession due in December 2026. 3 units booked out of 8 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bliss is a BMC-sanctioned project by M/s. Euphrosyne Infrastructure (OPC) Pvt Ltd in Cumballa Hill, Mumbai 400026, registered with MahaRERA as P51900047934. It was launched in December 2022. It has 13 units in 1 building: 7 homes (1, 2, 4 and 5+ BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 8 are for sale and 5 are rehab units for existing members.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.
3 units booked out of 8 units for sale (38%).