Dignity Bayview, Wadala West
by Dignity Realty And Housing · Wadala West, Mumbai 400031 · Map
- Launched
- Dec 20224 yrs originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 7 mths
- Concrete structure
- 85%Mid-construction
- Booked
- 111 of 19158%
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 63
- 2 BHK
- 58
- 3 BHK
- 58
- Other units
- 12
- Total units
- 191
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 0% | 111 | |
| 100% | 63% | 0% | – | |
| 100% | 63% | 0% | – | |
| 100% | 60% | 0% | 74 |
"–" means MahaRERA shows no figure for that update.
About this project
Dignity Bayview by Dignity Realty And Housing is a 191-unit SRA-sanctioned project in Wadala West, Mumbai 400031, launched in December 2022 with possession due in July 2027. 111 units booked out of total 191 units. The concrete structure (RCC) is 85% complete.
Read full summary
Dignity Bayview is an SRA-sanctioned project by Dignity Realty And Housing in Wadala West, Mumbai 400031, registered with MahaRERA as P51900048008. It was launched in December 2022. It has 191 units in 2 buildings: 179 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2027, extended by 7 months from the original December 2026. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.
111 units booked out of total 191 units (58%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 63% to 85% and the possession date has moved from December 2026 to July 2027.