Seventh Avenue, Mahalaxmi
by Rubberwala Housing & Infradevelopment LLP · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Jan 20233 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 78%Mid-construction
- Booked
- 162 of 32051% · 120 in Jul 2026
- Buildings
- 10.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 100
- 2 BHK
- 210
- Other units
- 10
- Total units
- 320
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 0% | 162 | |
| 100% | 18% | 0% | 120 | |
| 100% | 0% | 0% | 97 | |
| 100% | 0% | 0% | 65 |
"–" means MahaRERA shows no figure for that update.
About this project
Seventh Avenue by Rubberwala Housing & Infradevelopment LLP is a 320-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in January 2023 with possession due in December 2026. 162 units booked out of total 320 units. The concrete structure (RCC) is 78% complete.
Read full summary
Seventh Avenue is a BMC-sanctioned project by Rubberwala Housing & Infradevelopment LLP in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900048564. It was launched in January 2023. It has 320 units in 1 building: 310 homes (1 and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started.
162 units booked out of total 320 units (51%). Since the July 2026 update, 42 more units have been booked and the reported concrete structure (RCC) has gone from 18% to 78%.